Several sources are reporting the explosion was due to hydrogen which is used to cool the Callide C generator near Biloela Qld.


Can not help the Fed Gov as they try to blabber about future “hydrogen economy” in our energy mix.


Paywalled but says “…leak of the highly combustible hydrogen that’s used to cool the generator.”


www.couriermail.com.au › questnews › news-story
6 hours ago —

A hydrogen leak could be behind the explosion that led to the … leak of the highly combustible hydrogen that’s used to cool the generator.

Mr Brunker said the repairs to the unit at Callide C would take “months if not … A 550m exclusion zone is in place at Callide Power Station after fire in one of its turbines.


ABC and Brisbane Times articles also both mention hydrogen.

OpenNem and AEMO NEM dashboard show details of prices and generation.